Building Demolition + Phase II

Our team has been very busy working on-site and to date we have disconnected utilities, installed construction gates, fencing, historic wall bracing and conducted selective demolition. Starting tomorrow we will begin building demolition and you may experience increased noise and vibrations.
We are also approaching Phase II of construction which will focus on earth retention, foundation, and structure work. This phase of construction is anticipated to last through late spring of 2020.
If you need to speak to someone about specific details please reach out to our project manager Brad Hribar at 312.714.8519.