Concrete Work This Week
Scope of Work
We will begin to pour concrete this week and wanted to provide you with an update of what to expect on-site.
There will be 23 trucks on Tuesday, March 24, 2020, and 7 trucks on Thursday, March 26, 2020, that will be entering and exiting the site throughout the day. Truck traffic will be through the gate on Monarch and Hyman. The frequency of the trucks in the alley will be every 20 minutes.
The trucks will exit right on Monarch then turn left into the alley between Hopkins and Main Street where they will then do their washout into steel containers on private property located at 201 Main St with the permission of the property owner.
Washouts will take approximately 10 minutes. After they complete their washout they will make a right from the alley onto Aspen St. and then exit left onto Main St.
Construction Hours
Tuesday: Construction will begin at 8:00 a.m. and continue until approximately 5 p.m.
Thursday: Construction will begin at 8:00 a.m and last for about 3 hours.