Project Kick Off
The project has received its building permit and will begin staging the construction site shortly. Phase I will focus on prepping the site for building demolition and prepping Hyman Avenue to change from a two-way road to a one-way road with traffic flowing towards Mill Street. This will include the installation of construction fencing, re-striping Hyman Avenue, and creating pedestrian/cyclist protection barriers.
This process will start with the removal of building utilities, streetlights, signs, installing temporary electric, erecting the perimeter barriers, installing sound abatement, and installing bracing for the historic west and south masonry walls, replaced and new storefronts have been constructed across the entire south facade.