Project Work Begins!
Phase I has commenced with restriping Hyman Avenue to change from a two-way road to a one-way road with traffiic flowing towards Mill Street (September 5th).
This will include the installation of construction fencing, re-striping Hyman Avenue, and creating pedestrian/cyclist protection barriers (September 9th).
Construction during this phase will focus on prepping the site for building demolition This process will start with the removal of building utilities, streetlights, signs, installing temporary electric, erect-ing the perimeter barriers, installing sound abatement, and installing bracing for the historic west and south masonry walls.
We are working hard to ensure as little disruption as possible to our neighbors – but we realize that certain disruptions are unavoidable.
If you have any questions or concerns, please contact our project team, Brad or Reilly, and we will do our best to assist you.