Author Archives: crystal_admin

Reduced Encroachment on Monarch Street

Posted on

Over the next few weeks CENTAUR will be reducing our encroachment along Monarch. We will pull in the barricades and barriers which means we will be returning three parking spaces. Along with this, we will also be providing a temporary sidewalk from Hyman north to the alley. This means construction work in the street on…

3rd Floor Concrete Pours

Posted on

We will be pouring Floor 3 on Tuesday, March 30th starting at 8:00 am. Throughout the day there will be about 30 trucks in and out of the site, so please expect increased truck traffic in the area. Alleyway access will be closed off in the morning but will open back up in the afternoon….

Extended Alley Work Starting April 19th

Posted on

To Our Neighbors, The project will begin extended alley work on or around April 19th which is expected to take 3-4 weeks. The work will serve to bring upgraded gas, sewer, transformer, and relocated Comcast and CenturyLink services to the site. As we get closer to this phase of work we will confirm the start…

Concrete Pours January 21st

Posted on

Hi Everyone, We will be pouring Floor 2 on Thursday, January 21st starting at 8:30 am. Throughout the day there will be about 35 trucks in and out of the site, so please expect increased truck traffic in the area. We will follow the same washout path that we’ve used during previous pours. Feel free…

Truck Traffic Friday 12/4/20

Posted on

Tomorrow, Friday 12/4, we will be doing a concrete pour with about 35 trucks coming in and out of the site. Please expect higher than usual truck traffic surrounding the area. Most trucks will be utilizing the truck lane and a third will be using the alley.

Temporary Alley Changes

Posted on

This week the team narrowed the alley by approximately 2’ to accommodate for work happening on-site over the next three weeks.  During this time, there will be temporary chain link fence in place of the solid construction wall. Anyone with parking that is accessed from the alley will be able to access it from either…

Concrete Pour

Posted on

On Monday, August, 10th, the project team will be conducting concrete pours for Lower Level 1. There will be approximately 14 trucks driving to the site and the washout area. Please expect to see increased truck traffic on this day. We apologize for any inconvenience in advance. As always, please feel free to reach out…

Concrete Pour Schedule

Posted on

Next week on Tuesday 7/21, we have a scheduled concrete pour during which 12-14 trucks will be traveling in and out of our site. They will follow the same path used during previous pours and will do their washout behind Main Street Bakery.

Upcoming Truck Traffic

Posted on

During the months of May and June we will have sporadic truck traffic as we start another round of concrete pours. The trucks will exit right on Monarch then turn left into the alley between Hopkins and Main Street where they will then do their washout into steel containers on private property located at 201…

COVID-19 Safety Measures

Posted on

Our team has taken every measure to comply with local regulations and provide for the health and economic safety of our teammates as we re-open our site for construction. We have created a safety measure plan that outlines how we intend to manage our site and includes parameters for security, signage, personal protective equipment, symptom…

Pitkin County Requiring Construction Halt Until April 30th

Posted on

During this pause of work, CENTAUR is taking the following steps to ensure that we maintain our high-level of organization and cleanliness both on and off-site: In preparation of site closures, we worked with our different subcontractors to leave our sites clean, sanitized, and tidy. Our team and our community are always our top priority….

Concrete Work This Week

Posted on

Scope of Work We will begin to pour concrete this week and wanted to provide you with an update of what to expect on-site. There will be 23 trucks on Tuesday, March 24, 2020, and 7 trucks on Thursday, March 26, 2020, that will be entering and exiting the site throughout the day. Truck traffic…

Phase II

Posted on

Before taking a quick holiday break back in December 2019, our team completed the demolition of the building and the installation of all piles. We’re excited to announce that we’ve now started Phase II which will focus on excavation and earth retention – which is expected to be completed by spring. During this time, we…

Updated Construction Management and Outreach Plans

Posted on

The project team has updated its construction management and communications plans to reflect the updated conditions on-site, the current site plan and traffic flow, and the communications schedule. Links to these updated documents are on our home page. We are happy to answer any questions you may have about the minor changes. For changes to…

Transformer Work Today November 11th

Posted on

The transformer behind the Crystal Palace is being serviced today. During this time generators are being used to substitute power to those affected. We understand that this activity should take 24 hours to complete. Lassiter Electric is spearheading the repairs, so if you have any questions or concerns please contact Doug Lassiter at 970.618.2080.

Work on Monarch Street Monday October 21st

Posted on

The delivery of shipping containers for on-site storage and construction offices on Monday will necessitate crane work and reducing Monarch Street to a one-way for half of the day. There will be traffic control directing traffic but there may be impacts to parking and flows through Monarch Street. We apologize for any inconvenience. If you…